| ABV Rock Group Completed Projects |
|
| |
| Site 3 Buraidah Pipeline |
| Location: |
Buraidah |
| From: |
January 2004 |
| To: |
December 2006 |
| Description : |
Procure, construct, and pre-commission a 148 km. 12” Ø pipeline to connect the existing Qasim Bulk Plant to Buraidah Bulk Plant.
The project scope includes civil, structural, mechanical, cathodic protection, fire protection, electrical, communication, and instrumentation works related to Scraper trap facilities and Valve Stations. |
|
 |
| Site 7 Madinah to Yanbu Pipeline Project |
| Location: |
Madinah to Yanbu |
| From: |
June 2002 |
| To: |
December 2005 |
| Description : |
Procure, construct and pre-commission a 157 km. 14” Ø Below Ground pipeline to connect the existing Yanbu Refinery to the existing Madinah Bulk Plant. This pipeline encompassed laying of over 3 km within tunnels. |
|
 |
| Site 6 Abha Pipeline Project |
| Location: |
Abha |
| From: |
March 1997 |
| To: |
February 2004 |
| Description : |
Procure; construct and pre-commission a 250 km. below ground 14” Ø pipeline to connect the existing Jizan Bulk Plant to a new Bulk Plant to be erected by others in Abha. |
|
 |
| Site 5 Jeddah Pipeline Project |
| Location: |
Jeddah |
| From: |
December 1996 |
| To: |
2001 |
| Description : |
Procure, construct and pre-commission a 100 km. 12” Ø Below Ground pipeline to connect the existing Jeddah Refinery, the North Jeddah Bulk Plant and the new product storage caverns. |
|
 |
| Site 1 Riyadh Pipeline Project |
| Location: |
Riyadh |
| From: |
1995 |
| To: |
1999 |
| Description : |
Procure, construct and pre-commission twin 18 km. 10” Ø pipelines to connect the existing Riyadh Refinery to the new product storage caverns.
The project scope included civil, structural, mechanical, tank erection, cathodic protection, fire protection, electrical and instrumentation work related to Riyadh Refinery and Product Storage Caverns. |
|
|
|